logo

Lakeside Park*

  • Commencement of construction PHASE 01: 2006
    PHASE 02: In the pipeline
  • Project Opening PHASE 01: Q2 2008
    PHASE 02: TBC
  • Developer and property manager TriGranit
  • Total Development Cost in Euro 48 000 000
  • GLA (M2) PHASE 01: 24 650
    PHASE 02: 14 500
  • GBA (M2) PHASE 01: 32 900
    PHASE 02: 16 500
  • Parking Spaces PHASE 01: 508
    PHASE 02: 320
  • Designer hase 01: Adamson Associates Architects
    Phase 02: ABJ

Lakeside Park is a representative multi-phase development located in Bratislava the capital of Slovakia in a well-established business district in Bratislava III, the Nove Mesto area located only 4 km from Bratislava’s Old Town. Lakeside Park provides all users with easy access and ample secure parking. It is directly served by all modes of public transport including trams and busses with all amenities and services available at the nearby Polus City Center also developed by TriGranit. Nove Mesto train station is located in close proximity to the building. The first phase of the office complex completed in 2008 provides office, service / retail and storage space with 24 650 m2 of rentable area and features 5 floors averaging 1 750 m2 each, and 15 floors averaging 1 250 m2 each. Lakeside Park 01 offers their customers 508 car parking spaces. The building is considered as the one of the most modern high-rise office buildings in the city with a stabile and healthy tenant mix and untroubled reputation of the Landlord as well as the building itself. The major tenants are AT&T, Kone SSC and DuPont. The second phase of the office complex should be completed in the next years and will provide offices and amenities with approximately 13 000 m2 of rentable area. The offices will be situated on 12 floors averaging 1 200 m2 each. Lakeside Park Phase 02 will offer approximately  320 car parking spaces situated in secure underground parking levels. The amenities will be located on the ground floor of the building. The start of construction of Phase 02 office building is expected to be in 2015 – 2016. Further phases of the entire complex should follow.

*The marked projects are the former developments of the Group and due to the sale of the projects there is no legal relationship between the Group and these projects.